Project Overview

After a fire destroyed the Classrooms at Cowbridge Comprehensive School, Wernick Hire was awarded the contract to replace the facilities of 4 No. Classrooms in 2 No. Buildings, which had to be completed within 31 days.

Rapid response and flexibility was essential to meeting the requirements of the project, these are particular strengths of Mid Glam Construction and because of our experience and track record in emergency situations, Wernick Hire awarded us the contract to carry out the works.

Wernick Hire appointed Mid Glam Construction to facilitate all of the infrastructure requirements and erect & fit out the buildings on site.

Work Scope

  • Installation of 4 No. Classrooms in 2 No. separate Buildings
  • Groundwork’s Package, including alterations to existing levels
  • Ramps and Steps in accordance with DDA requirements
  • A programme of 31 days from acceptance of tender to completion of the buildings
  • Client
  • Wernick Construction
  • Site
  • Cowbridge Comprehensive School
  • Project
  • Emergency Classroom Installation