Project Overview
The de-commissioning of Hinkley Point A Nuclear Power Station required additional Office Administration space.
With almost 1900 m² of floor space encompassed in the 3 Storey Building, this was one of the largest Modular Building Facilities installed by Mid Glam Construction.
Our team met and exceeded the very high standards of Health & Safety required on this site, which resulted in them receiving Health & Safety Gold Medal Awards from the British Nuclear Group.
Work Scope
- Installation of 3 Storey, 72 Section Modular Building
- Manufacture and Install Building Anchors
- Complete building fit out including Atrium
- Installation of Suspended Bird Netting to roof of Building